The entire development was made by the officials of IT Division of DSIIDC. From analysis-mannual work -development-implementation –modification, everything was done by specialized It professional who worked under IT Division.
Being an IT head, I was faces several pitfalls for setting up the Division. Human has the nature to do the job as earlier was done. Very few were interested to change the traditional ways. So it was difficult for me for paradigm shift.
We trained the employee of the organization as per the need & requirements. We also imparted several in-house training for operation of Computer to develop the programme.
We stated out IT Division, so called then EDP Division .From 486 to P4 & 4 MB to 160 GB, we found marvelous changes from last 14 years. Now we have approximately 6 Servers, 200 Computers, 45 Printers, 10 Scanners and 10 Laptops.
Overall project plan development
• The challenges are faced in implementing of the projects was from the people. It is needless to mention that what is one of the important factor in the implementation of any project and if they do not cooperate whatever engineering or amount or time is spent the project can not run successfully.
Overall administration and coordination for projects
• Without co-ordination of management & staff of DSIIDC, it was impossible for us to implement the FTS. We got a lot of support at desired location.
One Point of Contact to DSIIDC’s staff and resources
• We imparted training to the employee of DSIIDC & make it sustainable to do the job independently.
Schedule development and monitoring
• We had prepared the module wise development schedules. The modules were added into single one. It was prepared under the certain period of framework & the entire process was monitored by me. We maintain the procedure of SDLC i.e Software development life cycle, which is used by our team to develop an information system, including requirements, validation, training, and user ownership. It results in a high quality system that meets or exceeds customer expectations, within time and cost estimates, works effectively and efficiently in the current and planned Information Technology infrastructure, and is cheap to maintain and cost-effective to enhance.
• Initiation/Planning: It generate a high-level view of the intended project i.e FTS and determine the goals of the project.
• Requirements Gatherings And Analysis : The goal of systems analysis is to determine where the problem is in attempt to fix the system.
• Design: In systems design functions and operations are described in detail, including screen layouts, business rules, process diagrams and other documentation.
• Build or Coding: Modular and subsystem programming code will be accomplished during this stage.
• Testing: The code is tested at various levels in software testing. Unit, system and user acceptance testing are often performed.
• Operations and Maintenance: The deployment of the system includes changes and enhancements before the decommissioning or sunset of the system. Maintaining the system is an important aspect of SDLC. As key personnel change positions in the organization, new changes will be implemented, which will require system updates.
Guidance/ training in the standards development process, policy and procedures :
• Now it is time to train the officials of DSIIDC. We trained them accordingly and give the useful tips to operate the system.
|