A well-defined and clearly articulated Project Implementation Plan was devised before the start of this project, out-lining each and every activities of how the whole project shall be done and what will be necessary contingencies if in case of certain probabilities were envisaged such as delivery delays et al.
Thus, all the 6 - Process group areas were used in executing the project, i.e. of Initiating, Planning, Executing and monitoring, controlling and finally of closing of the project. As well as the 9 - Knowledge area management were used in order to break-down the whole implementation of this project into varied activities such as; integration, scope, time, costs, quality, human resources, communications, Risks and finally procurement management.
Starting from the project duration and the required resources were defined, allocated and each person involved in this implementation were called and their job description including what is expected from them was defined, understood and a signoff was taken thereof so as not have any deviations from its actual delivery. Also the project scope exclusions were articulately defined so as not to create any project delivery anomalies.
Project was monitored in the below way;
• Clear Project Description from project kickoff in terms of Goals, objectives and requirements
• Defined Project Scope and Plan
• Skill Set Requirement and resources availability from all stake holders
• Assumptions & Issues Schedule
• Deliverables & Acceptance Criteria Schedule / Effort
• Critical Success Factors Risk Summary
• Best Practices /Lessons Learnt/ Retro Feedback
• Communication Hierarchy and risk mitigation
• Communications & Status Meetings
• Change Control process
• Project Issue and Risk Management
• Project Resource Management
• Project Communications
This was followed by a methodology, if in case there is any deviation to the project scope and change management procedure will have to be raised so as to agree upon the new changes. Thus, all relevant responsibilities of the client and all the persons involved in successfully implementing of the RFID was defined, certain assumption made and a clearly well-defined milestones were assigned;
• Material delivery
• Completion of hardware installation and testing of the same
• Completion of User Acceptance Tests
• Documentation & Knowledge transfer
• Project Closure
• Signoff
• After go-live support and patching of user-level bugs and minor changes
The total cost of the whole RFID project implementation 1st Phase and 2nd Phase was in the range of approximately BHD 130,000 USD 345,000.
|