4. In which ways is the initiative creative and innovative?
|
The project was governed by three different layers to assure project application compliance as follows:
• Project Steering Committee (Chaired by H.E the Undersecretary, Ministry of Manpower)
• Project Implementation Committee (Chaired by Deputy DG, IT Planning & Development, Ministry of Manpower)
• Project Implementation Team (Headed by the Project Manager-MoMP)
Project Business Case:
As a pre-project activity, a business case was developed between Ministry of Manpower and the Central Bank of Oman (CBO); this document contained information stating the objectives/benefits of the system and broad statements on how the system would function.
Reference Document: MOMP-Business Case Concept-20130122-vi1.1
Project Statement of Work:
The document was developed with the scope of work that will be done to complete this project, mentioning what development is covered within the scope and what is not in order for the Project Implementation Team to have a clear reference.
The document also states functional requirements of the system and data process flows, as well as hardware technical requirements and scope of Phases I, II & III.
Reference Document: WPS-SOW-20130424-v1.02i
Project Schedule:
A project implementation schedule was developed to effectively track tasks, dependencies and project progress; the schedule was maintained by the Project Managers of both Ministry of Manpower and the Central Bank of Oman (CBO).
Reference Document: WPS System Development Schedule v2.0 - 20130929.mpp
Vendor Relationship:
The implementation team comprised of Ministry of Manpower outsourced developers that were responsible for building the system within the Ministry’s in-house, allowing very close coordination between the management and the developers. The outsourced development team attended all implementation team meetings and system testing sessions.
Change Management:
During the implementation period, the implementation team scheduled regular weekly meetings, possible changes were deliberated and recorded in the meeting minutes, and necessary changes were raised to the implementation committee for approval and assigned actions.
Risk and Issue Management:
Risks and issues were recorded in the “RAID Log” matrix; the sheet contains the implementation team’s assessment for each risk and issue regarding project impact and criticality. RAID stands for Risks, Actions, Issues & Dependencies, as the document also contains information about important actions to be taken and project related dependencies.
Reference Document: WPS RAID Log.xml
|
|
5. Who implemented the initiative and what is the size of the population affected by this initiative?
|
The MOMP has a lot of departments, 35 branches in the different locations, and is integrated with other government entities. A technology project of this nature requires the entire range. MOMP demonstrated the plan and the role played by all stakeholders working together as a team. MOMP studied the background of these complaints and managed a committee to address employee wage issues. During the phase of analyzing and gathering requirements, the MOMP and CBO decided to involve some of employees, employers and local banks to determine their needs by distributing questionnaires and collecting their suggestions to enhance the system analysis.
The Stakeholders in this project are:
• Ministry of Manpower - The Project sponsor and hosting the application.
• Central Bank of Oman – Project Management and Interface with banking Systems and liaising with Banks
• Commercial Banks – Provide salary Data
• Royal Oman Police and Ministry of Commerce & Industry – Data Source to validate employee/employers
• Employers – update the latest Salary and other data with Manpower
• Employees – Required to open a Salary account with any of the commercial banks
• Sanad Offices- will be facilitating employers to in updating employment contracts on a periodic basis
• Public Authority Social Insurance – Interface with WPS for extracting the Pension contribution data.
• Local IT company - has worked together with MOMP; has developed several applications and provided training for employees and public.
• Media: helped to disseminate information through newspaper, ministry website and social media
|
6. How was the strategy implemented and what resources were mobilized?
|
The project was governed by three different layers to assure project application compliance as follows:
• Project Steering Committee (Chaired by H.E the Undersecretary, Ministry of Manpower)
• Project Implementation Committee (Chaired by Deputy DG, IT Planning & Development, Ministry of Manpower)
• Project Implementation Team (Headed by the Project Manager-MoMP)
Vendor
The implementation team comprised of Ministry of Manpower outsourced developers that were responsible for building the system within the Ministry’s in-house, allowing very close coordination between the management and the developers. The outsourced development team attended all implementation team meetings and system testing sessions.
Financial
The Ministry of Manpower funded the project, The estimated cost of the entire project was 777K US$ (300K OMR). The project used technical infrastructure created under the new hardware and software. The role of the MOMP's IT department as an owner of the project was to conceptualize the project, coordinate with various stakeholders who were involved in developing the entire technical infrastructure of the project including hardware and software, providing connectivity to the Data Centre and other entities, as well as the management of the setting up of data security and providing training.
|
|
7. Who were the stakeholders involved in the design of the initiative and in its implementation?
|
The WPS is notified of wages transactions for almost 2M employees every month and provides service to G2C and G2B, making a one stop e-government shop. With centralized architecture, the system can be accessed from anywhere by mobile application or the MOMP's portal.
The system has reduced the duration of problem- solving from six months to one week, compared to the earlier situation in which employers were not paying salaries to their employees for three to six months. Currently, MOMP inspection employees can receive an automated notification of wages delay within one week, and they can make an investigation and solve the problem within the same week, before it becomes critical.
For example, the last statistics of wage protection system found that the target group was around 293K employees work in 7,086 private sector entities.
(Reference Document: WPS DataCoverage [July 2014].xlsx)
This initiative has also helped to create an accurate data base that can allow the MOMP employees to monitor and control the issues of equal pay for men and women. Many government entities are dependant on the WPS for monitoring and controlling a variety of activities such as money laundering, fraud and terrorism.
|
|
8. What were the most successful outputs and why was the initiative effective?
|
The document was developed with the scope of work that will be done to complete this project, mentioning what development is covered within the scope and what is not in order for the Project Implementation Team to have a clear reference. The document also states functional requirements of the system and data process flows, as well as hardware technical requirements and scope of Phases I, II & III.
Project Schedule:
A project implementation schedule was developed to effectively track tasks, dependencies and project progress, the schedule was maintained by the Project Managers of both Ministry of Manpower and the Central Bank of Oman (CBO).
Reference Document: WPS System Development Schedule v2.0 - 20130929.mpp
.
Change Management:
During the implementation period, the implementation team scheduled regular weekly meetings, possible changes were deliberated and recorded in the meeting minutes, and necessary changes were raised to the implementation committee for approval and assigned actions.
Risk and Issue Management:
Risks and issues were recorded in the “RAID Log” matrix; the sheet contains the implementation team’s assessment for each risk and issue regarding project impact and criticality. RAID stands for Risks, Actions, Issues & Dependencies, as the document also contains information about important actions to be taken and project related dependencies.
|
|
9. What were the main obstacles encountered and how were they overcome?
|
Main Obstacles
The main obstacles concerned the quality of the data. The MOMP, banks and other government entities had data that was not unified and had some errors. The information required a lot of work in order to be updated and unified with local banks and government entities.
Another obstacle was that majority of workers in the private sectors did not have bank accounts that enabled the employers to wire their employee wages. With such a large number of workers, it was difficult for the banks to organize these workers to open their accounts in a short period of time.
Method of overcoming obstacles
To overcome this problem, the MOMP worked closely with local banks, government entities, employers and the public to make sure employees and employers data was unified, updated and integrated according to the employees' contract and government procedure.
The MOMP and CBO agreed to offer additional working hours at the local banks in order to absorb the large number of employees. The local banks offered services to the employers by sending their employees to the company site to facilitate the task of opening bank accounts. Due to the combined cooperation of banks, government entities, employers and citizens, the MOMP was able to reach its goal.
|